Construction at the Ust-Luga Sea Port progress report as per the end of 2019

Customer: JSC “Company Ust-Luga”.

Construction investor: Novotrans Group of Companies

Construction period: April–December, 2019 


Summing up the results of 2019, we would like to inform you about construction progress at the Ust-Luga Sea Port within the “Artificial Land Plots for Construction of Sea Terminals of the 5th and 6th Stages of General Cargo Complexes in the Ust-Luga Sea Port” facility:

  • production of sand geotextiles sacks – 62,367 pcs;
  • pile shells driving – 813 pcs; pipe pile – 32 pcs; sheet pile L5-UM – 2,642 pcs;
  • diking dams sand dumping – 259,200 m3;
  • sloping bank protection – 23,810 m3. of stone and crushed stone;
  • territory development using sand – 1,030,000 m3