Construction at the Ust-Luga Sea Port progress report. Period: March, 2020
Customer: JSC “Company Ust-Luga”
Construction investor: Novotrans Group of Companies
Construction period: March, 2020
Facility: “Artificial Land Plots for Construction of Sea Terminals of the 5th and 6th Stages of General Cargo Complexes in the Ust-Luga Sea Port”.
The vertical protection work is complete, the last pile shells were driven at the point and all sheet piles were also driven.
Installed in total:
- pipe pile – 769 t (32 pcs)
- sheet pile – 3,585 t (2,642 pcs)
- pile shell – 11,015 t (813 pcs)
All construction works are being executed according to the schedule.
See video of construction at the Ust-Luga Sea Port progress report