Construction at the Ust-Luga Sea Port progress report. Period: March, 2020

Customer: JSC “Company Ust-Luga”

Construction investor: Novotrans Group of Companies

Construction period: March, 2020

Facility: “Artificial Land Plots for Construction of Sea Terminals of the 5th and 6th Stages of General Cargo Complexes in the Ust-Luga Sea Port”.

The vertical protection work is complete, the last pile shells were driven at the point and all sheet piles were also driven.

Installed in total:

  • pipe pile – 769 t (32 pcs)
  • sheet pile – 3,585 t (2,642 pcs)
  • pile shell – 11,015 t (813 pcs)

All construction works are being executed according to the schedule.