Construction at the Ust-Luga Sea Port progress report. Period: April, 2020

Customer: JSC “Company Ust-Luga”

Construction investor: Novotrans Group of Companies

Construction period: April, 2020

Facility: “Artificial Land Plots for Construction of Sea Terminals of the 5th and 6th Stages of General Cargo Complexes in the Ust-Luga Sea Port”.

  • Generation of ALP cells of 5th and 6th stages is completed, total volume of sand filling is 1,735,000 m3 in solids.
  • Construction of temporary passage in quay apron is completed, pavement made from PAG-18 slabs: 11,690 sq. m.
  • Work on securing of cells using crushed stone are 65 % complete.

All construction works are being executed according to the schedule.