Completion of work stage in commercial seaport in Ust-Luga
In July 2017, the Construction management completed one of the stages in construction of pile base for port protecting structure offshore in Souther region of Commercial seaport in Ust-Luga. Section No. 2.
During construction 972.1 t of inclined pile shells Ø1,220×12(14) mm and 55.55 t of fastening metal structures were installed and mounted.
Construction management GT Morstroy has been working at this facility since 2014. Works are performed at several stages. As of today:
- 2,745.35 t of pipe piles were installed and mounted;
- 4,960.60 t of inclined pile shells Ø1,220×12(14) mm were installed;
- 393.25 t of fastening metal structures were mounted;
- 570.9 t of vertical pile shells Ø1,220 mm were installed and static pile shells were driven.
All works were completed within agreed timeframe and with due quality.